Progres Normalisasi Saluran Jalan Danau Dampelas Capai 63 Persen

Channel Normalization on Jalan Danau Dampelas Reaches 63 Percent

The water channel normalization on Jalan Danau Dampelas, RT 18/04, Bendungan Hilir Urban Village, Tanah Abang has reached 63 percent. The work has been running by Central Jakarta Water Resource Sub-agency since early January ago.

hopefully it can finish in March

Tanah Abang Sub-district Water Resource Implementer Unit Head, Eli Menawan Sari said the normalization is run to respond local resident's request since the area is often inundaten during heavy rain.

"Some of the plasters have broken and this causes the channel narrowing down," she said, Tuesday (2/4).

Channel Normalization on Jalan Arjuna Reaches 30 Percent

Eli explained the channel on Jalan Danau Dampelas has 60 cm of width, 80 cm height, and 140 m length.

"We deploy eight taskforce personnel for this work," she explained.

Eli added that the normalization is run by retracing the channel, installing u-ditch concrete and cober plate.

"Now the progres reaches 63 percent and hopefully it can finish in March," she added.

Meanwhile, one of local residents, Rahmat, appreciated the channel normalization in his area. He hopes the channel will funtion maximally.

"It is hoped the area will be free from inundation," he hoped.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1316 personFakhrizal Fakhri
  2. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1157 personDessy Suciati
  3. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye942 personNurito
  4. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye903 personBudhi Firmansyah Surapati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye844 personDessy Suciati